CLAYTON DATA CENTRE

CLIENT: TELSTRA

LOCATION: CLAYTON, VICTORIA

YEAR: 2020

PROJECT VALUE: $2.6 MILLION

The BGIS Projects team delivered this uninterruptible power supply (UPS) and main switchboard (MSB) upgrade project on time and budget, and to the satisfaction of the client’s original concept design requirements brief, despite the challenge of working through the COVID-19 pandemic. The project included the integration of a new MSB control function (ATS controller) and 1200kVA Modular UPS and battery system with no down time to the live IT load contained within the Zone 4 raised floor.